Q) A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
a) 5 days b) 6 days c) 10 days d) 11 days
Ans:
A’s 1 day work = 1/24
B’s 1 day work = 1/9
C’s 1 day work = 1/12
∴ (A + B + C)’s 1 day work = 1/24 + 1/9 + 1/12 = 17/72
∴ (B + C)’s 1 day work = 1/9 + 1/12 = 14/72
∴ (B + C)’s 3 day work = 3 x 14/72 = 7/12
∴ Balance work = 5/12
Time taken by A to complete 1/24 work = 1 day
∴ Time taken by A to complete 5/12 work = 1 x (5/12)/ (1/24) = 10 days
Hence, Answer is [C].