(Q) A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days, find the time taken by B to finish the work.
Ans: Let’s assume B alone takes X days to finish the work.
(Note: Here, we take X for B because we need to find time taken by B)
Therefore, A alone can finish it in (X – 6) days.
(Note: it was given that A takes 6 days less than B)
Therefore, A’s one day’s work =
and B’s one day’s work =
Next, it is given that A + B, both together finish the work in 4 days,
Hence, (A + B)’s one day’s work =
Now, work done by A in a day and work done by B in a day will be equal to work done by both in a day.
therefore, (A’s one day’s work) + (B’s one day’s work) = (A + B)’s one day’s work
Lets put the values:
Here we reject X = 2 because if X = 2, X – 6 will be – 4 but number of days can not be negative,
Therefore, X 2 and only X =12.
Hence, B alone can finish the work in 12 days.
Check:
If B can finish the work in 12 days, his one days’ work is
A will finish the work in 12 – 6 i.e. 6 days, hence his one days’ work is
Now = one day’s work together
Since, here both finish the work in 4 days, hence our answer is correct.