Q) A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is:
a) 1/4 b) 1/10 c) 7/15 d) 8/15
Ans:
A’s 1 day’s work = 1/15
B’s 1 day’s work = 1/20
∴ (A + B)’s 1 day’s work = 1/15 + 1/20 = 7/60
∴ (A + B)’s 4 days work = 4 x 7/60 = 28/60
∴ Balance work = 1 – 28/60 = 32/60 = 8/15
Hence, Answer is [D].