Q) A can finish a work in 45 days and B can do the same work in 40 days. If A and B started working together and after some days A left. B continued working and finished the balance work in 23 days. How many days did A work?
a) 5 days b) 7 days c) 9 days d) 11 days
Ans:
A’s 1 day work = 1/45
B’s 1 day work = 1/40
∴ (A + B)’s 1 day’s work = 1/45 + 1/40 = 17/360
Let’s consider that A left after X days.
∴ work done by (A + B) in X days = 17X /360
∴ Balance work = [1 – 17 X/360] ……… (i)
This work was finished by B in 23 days
∵ Work done by B in 1 day = 1/40
∴ Work done by B in 23 days = 23/40 ….. (ii)
[1 – 17 X/360] = 23/40
∴ 360 – 17 X = 23 x 360/40 = 23 x 9 = 207
∴ 360 – 207 = 17 X
∴ 17 X = 153
∴ X = 153/17 = 9 days
Hence, Answer is [C]